CONSTRUCTION PROGRESS UPDATE FOR Q2 THAO DIEN
By the end of August 2020, the construction works of Q2 Thao Dien project as follow:
• The electric power system of the project has been completed
• The facade of Shoplots is in the finishing process
• Facilities floor is on well track in progress
• Piling work and sheet piles are underway for Townhouses and Villas